PMP 情景题练习:三大领域覆盖,逐题解析(含错误选项原因),错题自动进错题本。
题库以情景单选为主,贴合 PMP"作为项目经理,你首先/最好应该做什么"的考法;每题给出错误选项原因,帮你建立决策思路。
现状:专题打样题(随章节扩充)。配合学习资源页的开源 8 套模拟题(共约 800 题) 做限时训练,效果最佳。
{"bank":[{"analysis":"ECO 三大领域为人员(People)、过程(Process)、业务环境(Business Environment);启动/规划/执行是过程组,范围/进度/成本是知识领域,预测/敏捷/混合是开发方法分类。","answer":"B","chapter":"PMP·考试全景","difficulty":1,"explain":{"A":"过程组是项目管理的阶段逻辑,不是 ECO 的领域划分。","C":"范围、进度、成本属十大知识领域中的内容。","D":"预测型/敏捷/混合是开发方法的分类维度。"},"id":"pmp-01-001","options":["启动、规划、执行","人员、过程、业务环境","范围、进度、成本","预测型、敏捷型、混合型"],"source":"chapter","stem":"按现行 PMP 考试内容大纲(ECO),考试覆盖的三大领域是?","subject":"项目管理","type":"single"},{"analysis":"现行考纲下预测型与敏捷/混合方法各约占一半,因此必须同时掌握传统过程与敏捷实践。","answer":"B","chapter":"PMP·考试全景","difficulty":1,"explain":{"A":"只考预测型是旧考纲的印象,已不适用。","C":"敏捷并非全部内容。","D":"业务环境占比最小(约 8%,示例口径)。"},"id":"pmp-01-002","options":["全部为预测型","各约一半","全部为敏捷","以业务环境为主"],"source":"chapter","stem":"PMP 考试中,预测型(瀑布)与敏捷/混合方法所占比例大致是?","subject":"项目管理","type":"single"},{"analysis":"报名需提供 35 小时项目管理教育证明,并满足相应项目经验要求(本科及以上 36 个月 / 大专及高中 60 个月,示例口径)。","answer":"B","chapter":"PMP·考试全景","difficulty":1,"explain":{"A":"培训证明是报名硬性材料之一。","C":"小时数不是 100 小时。","D":"与国内软考证书无关。"},"id":"pmp-01-003","options":["无需培训,直接报名","需 35 小时项目管理教育证明","需 100 小时培训","需先取得软考证书"],"source":"chapter","stem":"PMP 报名条件中,关于项目管理培训的要求是?","subject":"项目管理","type":"single"},{"analysis":"八大绩效域为干系人、团队、开发方法与生命周期、规划、项目工作、交付、测量、不确定性;采购属于知识领域(过程层面),不是绩效域。","answer":"D","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"干系人是八大绩效域之首。","B":"团队是绩效域之一。","C":"测量是绩效域之一。"},"id":"pmp-02-001","options":["干系人","团队","测量","采购"],"source":"chapter","stem":"PMBOK 第七版提出的八个项目绩效域不包括下列哪一项?","subject":"项目管理","type":"single"},{"analysis":"绩效域不是阶段,而是贯穿项目的关注维度,八者同时存在、相互影响,需要整体平衡。","answer":"B","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"把它们当作顺序阶段是常见误解。","C":"只关注交付会忽视不确定性与团队等维度。","D":"绩效域与知识领域、过程组是不同维度的概念。"},"id":"pmp-02-002","options":["它们是按时间先后完成的八个阶段","它们同时存在、相互依赖,需要项目经理平衡","只需关注「交付」绩效域即可","它们与项目知识领域完全等同"],"source":"chapter","stem":"关于八大绩效域,下列说法正确的是?","subject":"项目管理","type":"single"},{"analysis":"项目应聚焦价值:未被需要的功能属于镀金,浪费成本与工期,还可能造成验收争议。","answer":"B","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"未被要求的功能不等于价值提升。","C":"超支本身已构成偏差,不能简单视为可接受。","D":"与风险储备无关。"},"id":"pmp-02-003","options":["提升了客户满意度,属于好事","交付了客户不需要的功能,浪费资源且可能被视为镀金","违反成本基准但可接受","属于必要的风险储备"],"source":"chapter","stem":"团队为满足「更多功能」而交付了客户并未要求的功能,从价值交付角度看,最主要的问题是?","subject":"项目管理","type":"single"},{"analysis":"章程由发起人/高层签发,作用是正式授权项目、任命项目经理并给出高层级目标;详细 WBS 属规划阶段产物。","answer":"B","chapter":"PMP·启动整合治理","difficulty":1,"explain":{"A":"项目经理可参与起草但无签发权。","C":"章程是启动阶段的产物。","D":"详细 WBS 不在章程中。"},"id":"pmp-03-001","options":["由项目经理编写并自行签发","由发起人或高层签发,正式授权项目并任命项目经理","在项目收尾阶段编制","其中包含详细的工作分解结构"],"source":"chapter","stem":"关于项目章程,下列说法正确的是?","subject":"项目管理","type":"single"},{"analysis":"敏捷项目通过产品负责人对待办列表持续排序来吸收变化,而不是依赖传统变更控制委员会流程。","answer":"B","chapter":"PMP·启动整合治理","difficulty":2,"explain":{"A":"CCB 审批是预测型项目的典型机制。","C":"团队投票不是需求优先级的决定机制。","D":"发起人不负责逐项需求排序。"},"id":"pmp-03-002","options":["提交变更请求并由 CCB 审批","由产品负责人对待办列表(Backlog)持续排序","由团队成员投票决定","由发起人每季度批准"],"source":"chapter","stem":"在敏捷项目中,需求优先级的调整主要通过什么机制实现?","subject":"项目管理","type":"single"},{"analysis":"阶段关口是治理节点:评审阶段成果与商业价值,作出继续、调整或终止项目的决策。","answer":"B","chapter":"PMP·启动整合治理","difficulty":2,"explain":{"A":"日常决策仍由项目经理负责。","C":"与薪酬无关。","D":"关口评审不能替代验收测试。"},"id":"pmp-03-003","options":["代替项目经理做日常决策","在阶段结束时评审是否继续投入,决定继续/调整/终止","确定团队成员薪酬","替代验收测试"],"source":"chapter","stem":"阶段关口(Phase Gate)评审的主要作用是?","subject":"项目管理","type":"single"},{"analysis":"速率=团队每个迭代平均完成的故事点数(或工作量),用于预测剩余工作需要的迭代数;故事点是单条故事的相对大小,燃尽图是剩余工作量的趋势图。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"故事点是相对估算单位,不是团队产能指标。","C":"燃尽图展示剩余工作量变化趋势,本身不是产能指标。","D":"关键路径属预测型进度方法。"},"id":"pmp-04-001","options":["故事点总数","速率(Velocity)","燃尽图斜率","关键路径时长"],"source":"chapter","stem":"在敏捷项目中,用于衡量团队每个迭代完成工作量的指标是?","subject":"项目管理","type":"single"},{"analysis":"燃尽趋缓通常意味着存在阻碍、范围增加或依赖等待;应先与团队在站会/回顾中定位原因,再调整待办列表与流程。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"加班不解决根因,且会损害团队可持续性。","C":"未经分析与干系人沟通就直接延期不专业。","D":"压缩测试会带来质量风险。"},"id":"pmp-04-002","options":["要求团队加班补进度","与团队一起查明阻碍(障碍/新增范围/依赖等待)并从待办列表与流程上处理","直接延长项目截止日期","减少测试以保证交付"],"source":"chapter","stem":"项目燃尽图在连续几个迭代中下降趋缓甚至持平。项目经理首先应当?","subject":"项目管理","type":"single"},{"analysis":"CPI=EV/AC=120/140≈0.857;典型偏差 EAC=BAC/CPI=300/0.857≈350 万元。","answer":"C","chapter":"PMP·范围进度成本","difficulty":3,"explain":{"A":"300 万元等于 BAC,隐含 CPI=1 的假设。","B":"320 万元是非典型算法 AC+(BAC−EV)=140+180=320。","D":"280 万元低于原预算,与超支事实矛盾。"},"id":"pmp-04-003","options":["300 万元","320 万元","350 万元","280 万元"],"source":"chapter","stem":"某项目 BAC=300 万元,检查点 EV=120 万元、AC=140 万元、PV=150 万元。按当前效率继续(典型偏差),EAC 约为?","subject":"项目管理","type":"single"},{"analysis":"资源平衡为解决资源过载可能调整活动时间、进而影响关键路径与工期;资源平滑只在浮动时间内调整,不改变工期。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"资源平衡可能延长工期。","C":"资源平滑不改变工期,这是它与平衡的关键区别。","D":"两者用于资源优化,不是进度压缩技术。"},"id":"pmp-04-004","options":["两者都不改变项目工期","资源平衡可能改变关键路径与工期,资源平滑不改变工期","资源平滑可能延长工期","两者都用于压缩进度"],"source":"chapter","stem":"关于资源平衡(Resource Leveling)与资源平滑(Resource Smoothing),说法正确的是?","subject":"项目管理","type":"single"},{"analysis":"敏捷强调仆人式领导:Scrum Master 为团队服务、清除障碍、保护团队免受干扰,促进团队自组织与持续改进。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"命令控制与自组织团队理念冲突。","C":"其职责不止行政事务,还包括教练与促进。","D":"技术决策应由团队承担,而非代替。"},"id":"pmp-05-001","options":["命令控制式领导","仆人式领导:服务团队、清除障碍、促进自组织","只负责行政事务","代替团队做技术决策"],"source":"chapter","stem":"在敏捷团队中,Scrum Master 最应体现的领导方式是?","subject":"项目管理","type":"single"},{"analysis":"测试驱动开发(TDD)与持续集成是敏捷中把质量内建(build quality in)的典型实践,属管理质量/预防导向。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"QC 侧重检验结果,此处强调事前预防与持续集成。","C":"外部失败成本指交付后发现的缺陷代价。","D":"范围确认是验收过程,与测试驱动开发不同。"},"id":"pmp-05-002","options":["控制质量(QC)活动","敏捷质量实践(TDD 与持续集成)","质量成本中的外部失败成本","范围确认"],"source":"chapter","stem":"为提升交付质量,团队在编码前先写测试用例,并保持频繁集成。这属于?","subject":"项目管理","type":"single"},{"analysis":"渠道数=N(N−1)/2=12×11/2=66 条。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"24 是 12×2 的误算。","C":"132 是 12×11,未除以 2。","D":"144 是 12×12,公式错误。"},"id":"pmp-05-003","options":["24","66","132","144"],"source":"chapter","stem":"项目组共 12 人(含项目经理)。若成员之间两两沟通,沟通渠道数为?","subject":"项目管理","type":"single"},{"analysis":"高权力低利益→令其满意:保持其对重大事项的知情与正面态度,不必用细节打扰。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"重点管理适用于权力与利益双高的干系人。","C":"随时告知适用于低权力高利益的干系人。","D":"高权力干系人不可忽视。"},"id":"pmp-05-004","options":["重点管理,每日同步细节","令其满意:简要汇报关键节点与重大风险","随时告知全部细节","不作管理"],"source":"chapter","stem":"某干系人权力高但对项目细节关注度低。按权力-利益方格,恰当策略是?","subject":"项目管理","type":"single"},{"analysis":"Spike 是用于调研与验证技术可行性的短周期活动,能在早期降低不确定性并调整方案。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"推迟到末期会使风险集中爆发,成本更高。","C":"直接取消可能损失价值,应先验证再决定。","D":"增加人力不能解决技术不确定性。"},"id":"pmp-06-001","options":["把该功能放到最后一个迭代","安排 Spike(技术探针)迭代先做可行性验证","直接取消该功能","增加编码人力"],"source":"chapter","stem":"团队对一项新技术方案把握不足。为降低技术不确定性,敏捷项目常采用的做法是?","subject":"项目管理","type":"single"},{"analysis":"范围不明确时难以定死总价,工料合同按固定单价×实际工作量结算,适合尽快启动;CPPC 应避免。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"FFP 要求范围相对明确才能合理报价。","C":"CPPC 激励超支,应避免使用。","D":"该类型仍以总价为基础,不适合范围不清的情况。"},"id":"pmp-06-002","options":["固定总价(FFP)","工料合同(T\u0026M)","成本加成本百分比(CPPC)","总价加经济价格调整"],"source":"chapter","stem":"项目需求范围不明确但必须尽快启动外包。最适宜的合同类型是?","subject":"项目管理","type":"single"},{"analysis":"敏捷中需求由产品负责人统筹排序:应评估价值与影响,纳入待办列表并排序,保护当前迭代目标,通过评审与发布计划体现变更。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":3,"explain":{"A":"直接插入会破坏迭代承诺与团队节奏。","C":"直接拒绝不符合敏捷的协作与价值导向。","D":"日常需求优先级的决策不应上交发起人。"},"id":"pmp-06-003","options":["立即让团队插入开发,满足客户","与产品负责人一起评估价值与影响,将需求放入待办列表并排序(必要时调整后续迭代)","直接拒绝客户,强调迭代内不可变更","报请发起人决定"],"source":"chapter","stem":"情景题:客户在迭代中途提出新需求,要求立即加入本迭代。作为项目经理/Scrum Master,最恰当的做法是?","subject":"项目管理","type":"single"},{"analysis":"情景题优先「先分析、再协作、后行动」:先定位偏差根因,再与团队/干系人商定纠正措施(如调整关键路径活动、变更范围或合理调整基准)。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"持续加班会造成倦怠与质量风险,且未解决根因。","C":"未经分析就申请延期不符合专业做法。","D":"削减测试会带来质量与验收风险。"},"id":"pmp-06-004","options":["继续加班直到赶上进度","分析偏差根因(关键路径、资源、范围变更)并与团队及干系人商定纠正方案","立即向发起人申请延期","削减测试范围以赶工"],"source":"chapter","stem":"情景题:项目进度落后,团队成员已连续加班三周。作为项目经理,最恰当的第一步是?","subject":"项目管理","type":"single"},{"analysis":"按示例口径,过程领域约占 50%、人员约 42%、业务环境约 8%;虽然人员占比也很高,但过程略高于人员。","answer":"B","chapter":"PMP·考试全景","difficulty":1,"explain":{"A":"人员约占 42%,略低于过程。","C":"业务环境占比最小(约 8%)。","D":"三者占比并不相同。"},"id":"pmp-01-004","options":["人员(People)","过程(Process)","业务环境(Business Environment)","三者完全相同"],"source":"chapter","stem":"按 ECO 三大领域的占比口径(示例),占比最大的领域是?","subject":"项目管理","type":"single"},{"analysis":"PMP 以情景单选题为主,考查在具体情境下的判断与决策;计算方法(如挣值)只是其中一部分,且预测型与敏捷各约占一半。","answer":"B","chapter":"PMP·考试全景","difficulty":1,"explain":{"A":"计算题占比有限,主要是情景判断。","C":"多选与匹配题只是少量题型。","D":"敏捷/混合内容约占一半。"},"id":"pmp-01-005","options":["以计算题为主","以情景单选为主,常问「项目经理首先/最好应该做什么」","全部为多选与匹配题","只考预测型项目知识"],"source":"chapter","stem":"关于 PMP 考试的题型特点,下列说法正确的是?","subject":"项目管理","type":"single"},{"analysis":"裁剪是根据项目情境对方法、过程与文档进行适配,是 PMBOK 7 的核心原则之一;镀金是主动添加客户未要求的功能。","answer":"A","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"B":"镀金属负面行为,与裁剪不同。","C":"范围蔓延指未受控的范围扩大。","D":"资源平衡是进度资源优化技术。"},"id":"pmp-02-004","options":["裁剪(Tailoring)","镀金(Gold Plating)","范围蔓延","资源平衡"],"source":"chapter","stem":"项目团队根据项目规模、复杂程度与组织环境,对过程、工具与文档详略程度进行调整。这一做法称为?","subject":"项目管理","type":"single"},{"analysis":"该原则强调组织与团队对变化的适应能力与受挫后的恢复力(韧性),允许在变化中调整计划与做法。","answer":"B","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"与「拥抱变化」的导向相反。","C":"变更按权限处理,并非一律上报发起人。","D":"原则不排斥敏捷等灵活方法。"},"id":"pmp-02-005","options":["严格按初始计划执行,不做调整","面对变化能快速调整并具备恢复能力","所有变更都必须上报发起人","只采用预测型方法"],"source":"chapter","stem":"PMBOK 7 原则中的「拥抱适应性和韧性」,最接近下列哪种含义?","subject":"项目管理","type":"single"},{"analysis":"商业论证论证项目的价值与可行性,位于章程之前;章程才负责正式授权与任命项目经理。","answer":"B","chapter":"PMP·启动整合治理","difficulty":1,"explain":{"A":"授权与任命是项目章程的作用。","C":"详细 WBS 由范围管理产生。","D":"验收标准来自需求与合同。"},"id":"pmp-03-004","options":["正式授权项目并任命项目经理","论证项目「值不值得做」的成本收益与可行性","规定详细的 WBS 结构","作为验收标准"],"source":"chapter","stem":"商业论证(Business Case)在项目启动中的主要作用是?","subject":"项目管理","type":"single"},{"analysis":"预测型项目中重大变更由 CCB 审批;敏捷项目则通过产品负责人对待办列表排序来吸收变化。","answer":"B","chapter":"PMP·启动整合治理","difficulty":2,"explain":{"A":"项目经理通常只审批一般性变更。","C":"团队投票不是变更审批机制。","D":"供应商无权审批本项目变更。"},"id":"pmp-03-005","options":["项目经理自行批准","变更控制委员会(CCB)","团队成员投票","供应商决定"],"source":"chapter","stem":"在预测型项目中,涉及基准与合同金额的重大变更通常由谁审批?","subject":"项目管理","type":"single"},{"analysis":"燃尽图趋平通常意味着遇到障碍、出现新增范围或等待依赖,应通过站会与回顾定位原因并调整。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"先定位原因再采取措施,盲目加班会损害可持续性。","C":"燃尽图未下降说明尚有余量未完成。","D":"燃尽图是敏捷进度可视化的重要工具。"},"id":"pmp-04-005","options":["团队效率下降必须加班","可能存在阻碍、依赖等待或范围增加,应在站会/回顾中定位原因","项目已提前完成","燃尽图无参考价值"],"source":"chapter","stem":"迭代燃尽图出现连续几天持平(不再下降)。最合理的解读是?","subject":"项目管理","type":"single"},{"analysis":"INVEST 原则:Independent(独立)、Negotiable(可协商)、Valuable(有价值)、Estimable(可估算)、Small(小)、Testable(可测试)。","answer":"A","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"B":"无此原则项。","C":"无此原则项。","D":"无此原则项。"},"id":"pmp-04-006","options":["Independent(独立)","Immediate(即时)","Internal(内部)","Iterative(迭代)"],"source":"chapter","stem":"敏捷中编写用户故事时常用的 INVEST 原则,其中 I 代表?","subject":"项目管理","type":"single"},{"analysis":"震荡期以冲突、角色竞争与分歧为特征;形成期是客气试探,规范期开始形成规则,成熟期高效自组织。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"形成期成员彼此试探、依赖领导。","C":"规范期团队已建立工作规则与信任。","D":"成熟期团队高效自主运转。"},"id":"pmp-05-005","options":["形成期","震荡期","规范期","成熟期"],"source":"chapter","stem":"团队刚组建后不久,成员间开始争夺角色、对工作方式产生分歧。此时团队处于塔克曼模型的?","subject":"项目管理","type":"single"},{"analysis":"合作/面对(Collaborating)以双赢为目标,通过开放讨论找到兼顾各方关切的方案,是冲突处理中最理想的方式。","answer":"D","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"撤退是暂缓或不处理。","B":"缓和强调求同存异、弱化分歧。","C":"强迫以职权压制一方。"},"id":"pmp-05-006","options":["撤退/回避","缓和/包容","强迫/命令","合作/面对"],"source":"chapter","stem":"两位核心成员就技术方案长期争执,项目经理组织双方深入讨论、共同寻找满足双方关切的解决方案。该做法属于?","subject":"项目管理","type":"single"},{"analysis":"EMV=概率×影响=20%×100=20 万元(期望损失)。","answer":"A","chapter":"PMP·风险采购与应试","difficulty":3,"explain":{"B":"80 万元是误用未发生概率(80%)计算的结果。","C":"100 万元是发生后的实际损失额,未乘概率。","D":"120 万元无计算依据。"},"id":"pmp-06-005","options":["20 万元","80 万元","100 万元","120 万元"],"source":"chapter","stem":"某风险发生概率 20%,一旦发生将造成 100 万元损失。其期望货币值(EMV,按损失计)为?","subject":"项目管理","type":"single"},{"analysis":"敏捷合同常采用渐进式明细、按迭代/增量计费(如工料合同)等方式,以适应需求演进;合同仍需规范管理,变更应按约定程序处理。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"固定总价合同在需求多变时易引发争议。","C":"敏捷项目同样需要合同规范各方责任。","D":"变更应按合同程序书面处理,并非一律无效。"},"id":"pmp-06-006","options":["必须采用固定总价合同","可采用按迭代或增量计费、渐进式明细的合同方式,鼓励协作与变更","敏捷项目不需要合同","合同变更一律无效"],"source":"chapter","stem":"关于敏捷项目中的采购/合同管理,下列说法正确的是?","subject":"项目管理","type":"single"},{"analysis":"现行 PMP 考试依据《考试内容大纲》(ECO)按人员、过程、业务环境三个领域组织,并融合预测型、敏捷与混合方法,而非仅按过程组与知识领域罗列。","answer":"B","chapter":"PMP·考试全景","difficulty":2,"explain":{"A":"五大过程组与十大知识领域是 PMBOK 第六版的框架,现行考试以 ECO 三领域为主。","C":"敏捷是重要组成,但考试同时覆盖预测型与混合方法。","D":"仅考预测型方法不符合现行考试实际。"},"id":"pmp-01-006","options":["五大过程组与十大知识领域的逐条罗列","人员、过程、业务环境三个领域(ECO 考试内容大纲)","仅敏捷实践","仅预测型(瀑布)方法"],"source":"chapter","stem":"现行 PMP 考试内容主要围绕下列哪一项组织?","subject":"PMP 项目管理","type":"single"},{"analysis":"PMP 情境题占比高,解题核心是判断「项目经理下一步最恰当的行动」:优先选择主动分析、遵循流程、与相关方协作的方案,避免越权决策、只汇报不行动或跳过流程的选项。","answer":"B","chapter":"PMP·考试全景","difficulty":2,"explain":{"A":"死记定义不足以应对情境题,需结合流程与原则判断。","C":"「技术上完美」但违反流程或越权的选项往往不是最佳答案。","D":"考试题量大、时间紧,需控制在每题约 1 分钟出头的节奏。"},"id":"pmp-01-007","options":["遇到情境题应先回忆知识点定义再作答","情境题应先判断项目经理「下一步最恰当的行动」,避免选择越权或只汇报不行动","所有题目只需选出技术上最完美的方案","题目数量少,可平均每题用时 5 分钟以上"],"source":"chapter","stem":"关于 PMP 考试的答题策略,说法正确的是?","subject":"PMP 项目管理","type":"single"},{"analysis":"十二项原则包括成为勤勉尊重关心他人的管家、营造协作的团队环境、与相关方有效协作、聚焦于价值、识别并响应系统交互、展现领导力行为、根据上下文进行裁剪、将质量融入过程和成果、驾驭复杂性、优化风险应对、拥抱适应性和韧性、为实现预期的未来状态而驱动变革;「固定使用预测型生命周期」不属原则,而是应据情境裁剪。","answer":"D","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"该表述属十二项原则之一。","B":"该表述属十二项原则之一。","C":"该表述属十二项原则之一。"},"id":"pmp-02-006","options":["成为勤勉、尊重和关心他人的管家","营造协作的团队环境","聚焦于价值","固定使用预测型生命周期"],"source":"chapter","stem":"PMBOK 第七版提出的项目管理十二项原则中,不包括?","subject":"PMP 项目管理","type":"single"},{"analysis":"八个绩效域为相关方、团队、开发方法与生命周期、规划、项目工作、交付、测量、不确定性;不确定性绩效域关注风险与模糊性等的识别与应对。","answer":"B","chapter":"PMP·原则与绩效域","difficulty":2,"explain":{"A":"相关方绩效域关注与相关方的识别、参与和协作。","C":"测量绩效域关注评估项目绩效与采取适当行动。","D":"交付绩效域关注项目成果与价值的交付。"},"id":"pmp-02-007","options":["相关方绩效域","不确定性绩效域","测量绩效域","交付绩效域"],"source":"chapter","stem":"PMBOK 第七版提出的八个项目绩效域中,负责「识别、分析并应对不确定性与风险」的是?","subject":"PMP 项目管理","type":"single"},{"analysis":"项目章程由发起人或高层管理者发布,正式授权项目存在、明确项目经理及其职权,并记录高层级需求、目标、总体里程碑、总体预算与主要相关方等。","answer":"B","chapter":"PMP·启动整合治理","difficulty":2,"explain":{"A":"详细进度安排属项目管理计划与进度基准的内容。","C":"项目章程是高层级文件,不能替代项目管理计划。","D":"变更请求通过实施整体变更控制流程处理与记录。"},"id":"pmp-03-006","options":["详细列出项目活动的进度安排","正式授权项目并为项目经理提供动用组织资源的权限","替代项目管理计划","记录项目过程中产生的变更请求"],"source":"chapter","stem":"项目章程的主要作用是?","subject":"PMP 项目管理","type":"single"},{"analysis":"实施整体变更控制流程为:提出变更请求并记录 → 评估对范围、进度、成本、质量等的影响 → 提交 CCB 或有权审批人决策 → 批准后更新计划与文件 → 通知相关方并跟踪实施。","answer":"B","chapter":"PMP·启动整合治理","difficulty":2,"explain":{"A":"未经审批直接实施变更会导致基准失控。","C":"一概拒绝会忽视合理变更需求,也不符合流程。","D":"搁置不处理会使问题累积并损害相关方参与。"},"id":"pmp-03-007","options":["直接实施变更以满足相关方要求","提出并记录变更请求,评估影响后提交变更控制委员会(CCB)审批","拒绝变更以保持基准不变","通知团队按原计划继续,暂不处理"],"source":"chapter","stem":"项目执行中相关方提出一项可能影响基准的变更,项目经理首先应当?","subject":"PMP 项目管理","type":"single"},{"analysis":"赶工(Crashing)通过增加资源(加班、增人、加急采购)压缩关键路径工期,通常增加成本;快速跟进(Fast Tracking)把原本顺序进行的工作改为并行,可缩短工期但增加返工与协调风险。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"增加资源缩短工期是赶工的定义,快速跟进是并行实施。","C":"两类技术均用于缩短关键路径上的工期。","D":"两种方法都会带来成本增加或风险上升,不存在「无代价压缩」。"},"id":"pmp-04-007","options":["快速跟进通过增加资源缩短工期,通常增加成本","赶工通过增加资源缩短关键路径上的工期,可能增加成本;快速跟进通过并行实施增加返工风险","两者都不改变关键路径","两者都能在不增加任何风险的情况下缩短工期"],"source":"chapter","stem":"关于「赶工」与「快速跟进」两种进度压缩技术,说法正确的是?","subject":"PMP 项目管理","type":"single"},{"analysis":"塔克曼团队发展阶段为形成期(Forming)、震荡期(Storming,冲突与角色争夺)、规范期(Norming,形成规范与凝聚)、成熟期(Performing,高效协作),另有解散期。","answer":"B","chapter":"PMP·质量资源沟通","difficulty":2,"explain":{"A":"形成期成员以礼貌试探为主,冲突不明显。","C":"规范期已形成工作规范与相互信任。","D":"成熟期团队运作高效、自主协作。"},"id":"pmp-05-007","options":["形成期","震荡期","规范期","成熟期"],"source":"chapter","stem":"团队建设阶段中,成员之间出现意见分歧与角色争夺的阶段是?","subject":"PMP 项目管理","type":"single"},{"analysis":"工料合同(T\u0026M)兼具成本补偿与固定总价的特点:按工时与材料单价计费,适用于范围不明确、需要快速启动的工作,同时可通过设定总价上限控制风险。","answer":"C","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"固定总价合同(FFP)对卖方风险最大,对买方风险较小。","B":"成本补偿合同对买方风险最大,卖方风险较小。","D":"合同类型直接决定风险在买卖双方之间的分担方式。"},"id":"pmp-06-007","options":["固定总价合同对买方风险最大","成本补偿合同对卖方风险最大","工料合同兼具成本补偿与固定总价的特点,适合工作量不明确但需快速开工的情形","合同类型选择与风险分担无关"],"source":"chapter","stem":"关于合同类型,说法正确的是?","subject":"PMP 项目管理","type":"single"},{"analysis":"SPI = EV/PV = 80/100 = 0.8 \u003c 1,表示进度落后;CPI = EV/AC = 80/90 ≈ 0.89 \u003c 1,表示成本超支。","answer":"B","chapter":"PMP·范围进度成本","difficulty":2,"explain":{"A":"SPI 与 CPI 均小于 1,与「超前、节约」相反。","C":"SPI \u003c 1 表示进度落后而非超前。","D":"CPI \u003c 1 表示成本超支而非节约。"},"id":"pmp-04-008","options":["进度超前、成本节约","进度落后、成本超支","进度超前、成本超支","进度落后、成本节约"],"source":"chapter","stem":"项目 PV = 100 万元,EV = 80 万元,AC = 90 万元,则该项目当前状态是?","subject":"PMP 项目管理","type":"single"},{"analysis":"转移通过保险、担保、外包或合同条款把风险的影响与责任转移给第三方,适用于概率低、影响大且自身难以控制的风险。","answer":"B","chapter":"PMP·风险采购与应试","difficulty":2,"explain":{"A":"规避是改变计划以消除风险或其成因,适用于可通过调整方案回避的情形。","C":"减轻是降低风险发生概率或影响,适用于可采取措施减少风险的情形。","D":"接受适用于影响较小或应对成本高于收益的风险。"},"id":"pmp-06-008","options":["规避","转移","减轻","接受"],"source":"chapter","stem":"对于发生概率低但影响大、且项目团队无法自行控制的风险,最适宜的风险应对策略是?","subject":"PMP 项目管理","type":"single"}],"cert":"pmp","chapters":[{"name":"PMP·考试全景","title":"第 1 章 · 考试全景与报名","url":"/pmp/books/jingjiang/pmp-01-kaoshi/"},{"name":"PMP·原则与绩效域","title":"第 2 章 · 原则与绩效域(PMBOK 7 思路)","url":"/pmp/books/jingjiang/pmp-02-yuanze/"},{"name":"PMP·启动整合治理","title":"第 3 章 · 启动、整合与治理","url":"/pmp/books/jingjiang/pmp-03-qidong/"},{"name":"PMP·范围进度成本","title":"第 4 章 · 范围、进度与成本","url":"/pmp/books/jingjiang/pmp-04-fanweijindu/"},{"name":"PMP·质量资源沟通","title":"第 5 章 · 质量、资源、沟通与干系人","url":"/pmp/books/jingjiang/pmp-05-zhiliang/"},{"name":"PMP·风险采购与应试","title":"第 6 章 · 风险、采购与情景应试策略","url":"/pmp/books/jingjiang/pmp-06-fengxian/"}],"practiceUrl":"/pmp/practice/"}